Alternatives are developed by DWR as part of completion of the EIR in accordance with CEQA, including consideration of scoping comments. Scoping comments will inform the development of alternatives. At this time, DWR has only asked DCA to evaluate the proposed project corridors specified in the NOP. Because it is more cost-effective to evaluate different flow capacities at one time, DWR also asked DCA to evaluate a flow capacity of 6,000 cubic feet per second (cfs) and three different flow capacities as alternatives (3,000; 4,500 and 7,500 cfs). However, it is not a commitment that the alternate flow capacities will be analyzed in detail as alternatives.